Lowell Boulevard Project Updates

Lowell Blvd. Project Updates
Sign Up for Email Updates

News & Updates

........................................................................................

July 6, 2017



WORK NOTICE - LOWELL BLVD. SOUTH OF MIDWAY - July 10 - July 22


The City's water main will have a water tap connection installed for the new development near this intersection.
This is not part of the Lowell North or Lowell South projects, but will further impact travel in this area.
Expect daily Lane closures and flagging activity between 8:30am and 4:00pm immediately south of Midway on Lowell Blvd., beginning Monday, July 10 through Saturday, July 22.

July 3, 2017


Lowell North is going very well.  North of Misty, the road is at full width and paved.   Median work in this area will continue in July.   The east half of the road from the Misty St. intersection to Trails Ave. has been reconstructed and was reopened the last week of June.   The expansion of the west half of the functional road between Paul Derda Rec Center and E. Midway is nearly complete with all curb, sidewalk and base layer paving done. The median curbs in this area are 90% complete.  The traffic signal conversion work at Westlake will begin in July.   We now have a replacement landscape contractor,  Western States Reclamation (WSR), for Lowell South.  All irrigation and plants are in south of 124th with final preparations being made for placement of sod in this area the first week of July.  Landscape restoration work will then focus on the Brandywine frontage north of 124th.   In mid July WSR will shift focus to the Lowell North project and begin building the new irrigation supply systems for the new median and roadside landscaping.

TOM FROST PARKING LOT RELOCATION - UPDATE
While the new, permanent parking lot is complete and open, the new street light at Westlake Drive will not be installed for another few weeks, making access from north-bound Lowell difficult.
Please continue to use alternative trail access parking instead of the new Tom Frost parking lot.  
See map below. To access trails, please park at PDRC, or County Commons.

Tom Frost Parking Update July 2017

PLEASE NOTE:

 

Be sure to add 5-8 minutes to your commute if you use Lowell Blvd.

 
Please plan on adding an extra 5-8 minutes to your trip if using Lowell Blvd between E Midway Blvd and W 136th Ave during construction.

Temporary lane closures, flagging and traffic back-ups should be expected through the summer while improvements to overhead utilities, expansion of the Tom Frost parking lot and added sidewalks, turn lanes and landscaping come to Lowell Blvd North. 
 
Construction zone work hours are anytime between 7 a.m. – 7 p.m., except for Sundays and Holidays.


AREAS OF INTEREST


Paul Derda Rec Center (PDRC)
Please plan on adding an extra 5-8 minutes to your trip as temporary lane closures, flagging and traffic back-ups should be expected through the summer. 

Tom Frost Parking lot relocation
New parking lot is complete.  Landscaping and other amenities are planned at a later date.

Commercial businesses
There has been minor non-invasive work occurring along these properties with no access restricting activities. Things should remain this way throughout the project duration.


BACKGROUND INFORMATION

Lowell North
The City and County of Broomfield and contractor Concrete Works of Colorado (CWC) will start construction on the the Lowell Boulevard North Improvement Project in March. This project is the final of seven projects identified in the 2006 Internal Transportation Improvement Program plan.

The following major project elements will be constructed on or along Lowell Blvd. from East Midway to West 136th Avenue:
  • Construct a two-lane arterial roadway section with bike lanes and center raised landscaped median;
  • Provide dedicated turn lanes at the intersections where warranted;
  • Complete all missing curb, gutter and sidewalk;
  • Landscape the east side of road between curb and sidewalk;
  • Landscape the west side of road along open space with less formal native materials;
  • Bury any existing overhead utilities;
  • Install stand-alone streetlights; and
  • Relocate and expand the Tom Frost Parking Lot

SCHEDULE


The project work will be performed in several phases over a period of 18 months with an anticipatedLowell North graphic timeline completion date of September 2018. Here are the three major phases:

  • PHASE I (West side of Lowell & Tom Frost Parking Lot): Improve all drainage & utility, road & sidewalks, and traffic signal changes from 136th Ave. to East Midway. Anticipated completion OCTOBER 2017. 
  • PHASE II (East side of Lowell and Median): Improve all drainage & utility, road & sidewalks, and remaining traffic signal changes from 136th Ave. to East Midway. Includes the final surface paving & marking of the entire project. Anticipated completion JUNE 2018. 
  • PHASE III Complete all irrigation systems and landscaping for the entire project. Anticipated completion AUGUST 2018. 

Travel Time Delays


The project zone will post a lower speed limit for the safety of everyone, and during non-peak travel hours (9 a.m. – 3:30 p.m. ) traffic flagging operations will be encountered. This may add up to eight minutes to travel time through the project.

Intersecting streets and business entrances will remain open during construction. Any short term access closures will be coordinated in advance with affected businesses and residents.

Click to view Concept Plans:
** These files are large and may take a while to load. If the files do not open, try a different browser.
Midway to PDRC South Entrance

PDRC South Entrance to Rabbit Mtn Rd/Trails Ave
Rabbit Mtn Rd/Trails Ave to W 136th Ave


LOWELL NORTH PROJECT OVERVIEW


Lowell North Project

Lowell North Project Description



The overall vision concept and need for the project was set by Council in the 2006 Internal Transportation Improvement Program plan. The 2006 project vision concept sketch and major project elements are shown above.

In 2008, a detailed scoping study and preliminary plan consistent with the 2006 concept was completed and contains these major project elements for Lowell Boulevard: 

• Construct a two-lane arterial roadway section with bike lanes and center raised landscaped median;
• Provide dedicated turn lanes at the intersections where warranted;
• Complete all missing curb, gutter and sidewalk;
• Landscape the east side of road between curb and sidewalk;
• Landscape the west side of the road along the Open Space with less 
formal native materials
• Bury any existing overhead utilities;
• Install stand-alone streetlights; and
• Relocate and expand the Tom Frost parking lot

In May 2011, the 2008 scoping plan was reevaluated based upon 2010 traffic data counts for each of the five signalized intersections within the project limit. Based upon this new data, adjustments were made to the forecasted traffic on Lowell to the year 2035. The analysis showed traffic would perform at optimum capacity or better through year 2035 except for the intersection at West 136th Avenue. Because of this analysis, the following improvement was added to the project scope:

Addition of a second southbound through lane starting 1,000 feet north of West 136th Avenue and extending past the West Metro Fire Station south of West 136th Avenue. 

The addition of a second southbound lane, as shown below, will improve the north and south operation of Lowell at West 136th Avenue through the 2035 design horizon. 

In February 2014, Council reviewed this project scope and awarded a consulting agreement to Merrick Engineering for final design and to prepare construction documents and plans for bidding.

In January 2017, after receiving bids from nine interested and qualified general contractors, Council awarded a construction contract to Concrete Works of Colorado (CWC). The contract, in addition to the Lowell road work, also includes relocation of the Tom Frost Reservoir parking lot, and completion of neighborhood entry signs and monuments for the Westlake neighborhoods. CWC will begin work in March. The many components of the project along the one mile corridor will be constructed over a 18 month period.

Lowell Through Lanes at 136th

Please be sure to sign up for Lowell Project email updates at the top of this page.
Comments or questions? Please email Noreen at ngardner@broomfield.org.