Quail Creek Channel - Westlake Lateral Drainage Improvements

NEWS AND UPDATES...

GoodLand poured the concrete walls and top deck for the Concrete Box Culvert at the eastern drainage structure (i.e. Diversion Structure) on Friday, October 16th.

During the week of October 19, 2020,  GoodLand will continue work on the Diversion Structure including backfilling the Concrete Box Culvert and pouring the concrete manhole structure.  The work on this drainage structure is anticipated to take two weeks to complete. 

Construction is currently on schedule and anticipated to be complete in November 2020.

We appreciate everyone's patience as construction continues on this important drainage project.


Quail Creek Oct 16 2020 2

Quail Creek Oct 16 2020

Quail Creek Channel Oct 2020Quail Creek Channel Oct 2020 2

Quail Creek Oct 2 2020
Quail Creek 9-11-20