Review Timelines

Construction is up all over the metropolitan area so building departments are busy! Please schedule enough time for a plan review to keep your project on track. Typical plan review times are as follows:

Water heaters, furnaces, and shingle re-roofs (between 4:12 & 6:12 pitch), permits are typically processed over the counter

Starting February 3rd, 2020 - Over the counter plan reviews (Basement Finish, Small Remodels, Decks, Pergola's, Patio Covers and any other permit that requires a plan reviewer) will only be available between 9 am to 1 pm Monday - Friday - If you are bringing in any plan review documents outside of this time frame or if you are bringing in a big project please be prepared to drop your plans off for review and we will call or email you once they are complete.

New house – custom or new model - 6 to 7 weeks for first comments

New house – master plan - 6 to 7 weeks for first comments

New house w/approved master plan - 5 to 6 weeks

New commercial – 6 to 7 weeks for first comments

Tenant finish - 5 to 6 weeks for first comments

Residential additions – 4 to 5 weeks for first comments

Solar PV Systems - 1 to 2 weeks

Signs - 4 to 5 weeks

Windows - 2 weeks

Estimated times above are goals, but are not guaranteed!