Review Timelines

Construction is up all over the metropolitan area so building departments are busy! Please schedule enough time for a plan review to keep your project on track. Typical plan review times are as follows:

Water heaters, furnaces, and shingle re-roofs (between 4:12 & 6:12 pitch), permits are typically processed over the counter - (On Hold "Due to the Coronavirus situation")

Over the counter plan reviews - (On Hold "Due to the Coronavirus situation) - (Basement Finish, Small Remodels, Decks, Pergola's, Patio Covers and any other permit that requires a plan reviewer) will only be available between 9 am to 1 pm Monday - Friday - If you are bringing in any plan review documents outside of this time frame or if you are bringing in a big project please be prepared to drop your plans off for review and we will call or email you once they are complete.

"Due to the Coronavirus situation" some of the review timelines below have changed:

New house – custom or new model - 7 to 8 weeks for first comments  

New house – master plan - 7 to 8 weeks for first comments

New house w/approved master plan - 7 to 8 weeks

New commercial –  7 to 8 weeks for first comments

Tenant finish - 7 to 8 weeks for first comments

Residential additions – 4 to 5 weeks for first comments (On Hold "due to the Coronavirus situation")

Solar PV Systems -  4 to 5 weeks

Signs - 4 to 5 weeks

Windows - 2 weeks (On Hold "due to the Coronavirus situation")

Estimated times above are goals, but are not guaranteed!